Size: ~1,440 ft2 Timeline: 8 weeks Year: 2016
Project Summary
The Regina Airport Authority hired Quorex Construction as a prime contractor and Pattison MGM as the architect to manage a number of expansions at their airport. One of the building projects was a screening facility for air side traffic. The project involved a pre-engineered steel building structure that vehicles could drive through, and needed to be attached to office space.
The Details
- Very high snow load requirement on modular building because of placement adjacent to pre-engineered building
- Special design considerations given to integration and connection to the pre-engineered building
- Strict architectural guidelines to be followed to ensure compliance with the rest of the airport expansion
- Structure had to accommodate being unloaded and placed at grade
- Very tight timeline